RFI, RFP, RFQ and the qualification questionnaire are different steps
An RFI is the first filter, and qualification comes later. The APIC best practices guide for managing suppliers, version 2 of 18 March 2024, groups the request for information, proposal and quotation into one stage it calls RfX. At that stage buyers ask for standard documentation packages, plus commercial terms such as price, payment terms and minimum order quantity.
Then the buyer's team, quality included, reviews the package. According to the same guide, that review decides whether there are risks, which extra questions to ask and whether a site visit is needed. Only after that does formal qualification start, with questionnaires, statements, audits and, for critical materials and services, a quality agreement.
Pharma companies ask because GMP guidance asks them to. Section 2.7 of ICH Q10, dated 4 June 2008, says the company should assess the suitability and competence of a supplier before choosing it, for example through audits, material evaluations or qualification. Point 5.27 of chapter 5 of the EU GMP guidelines asks for the selection and approval of starting material suppliers to be documented, with supervision in proportion to the risk.
What a pharma RFI usually asks
Most RFIs follow the same blocks, even when the form changes from one buyer to the next. The APIC guide lists what the RfX stage typically requests, besides the commercial terms. It was written for suppliers of API manufacturers, but the same blocks work for sorting what equipment and single-use buyers ask.
- Sustainability, CSR and environment, health and safety information, as a selection criterion.
- Legal compliance information and the financial status of the company.
- The supply chain, including the identity of manufacturers and subcontractors involved in the product.
- Transport routes and shipping risk assessments for sensitive materials.
- Capacity, capability and delivery performance.
- Product knowledge, such as manufacturing experience, quantities and batch size.
- Specifications, REACH aspects and high-level information on GMP status, quality system and regulatory track record.
- Your willingness to accept the buyer's qualification procedure, from questionnaires and statements to audits and quality agreements.
Is an RFI response a binding offer?
Usually it is not, because the RFI comes before the proposal and the quotation. Read the terms in the request itself, though, since some buyers ask you to confirm prices or lead times. If a figure may change, say until when it is valid. Keep anything commercial out of the quality answers so each document can be reviewed by the right team.
Which document answers each block
Every block in an RFI can be answered with a document or page you already have, or should have. The table links each block to its proof and to the person in your company who should own it. The owner keeps the document current and signs off each answer before it goes out.
For equipment makers there is an extra block. Point 3.5 of Annex 15 of the EU GMP guidelines says equipment should be confirmed against the URS at the vendor site before installation, where applicable, and point 3.7 says FAT may be supplemented by a SAT. Buyers will ask how you support that.
| RFI block | Document or page that answers it | Owner |
|---|---|---|
| Company profile and industries served | About page and a one-page company fact sheet | Marketing |
| Quality system and certificates | Certificates page with dated PDFs and a quality policy summary | Quality |
| Capacity and delivery performance | Capacity statement with lead times by product line | Operations and sales |
| Supply chain and subcontractors | Supply chain statement naming manufacturing sites | Quality and purchasing |
| Specifications and materials | Datasheets and specification sheets with version and date | Engineering |
| Regulatory statements | Signed statement templates, such as REACH and BSE or TSE | Quality and regulatory |
| Change notification | Written change notification policy | Quality |
| Qualification support for equipment | Index of the documentation pack and an outline of FAT and SAT | Engineering |
| References | Anonymised cases approved by the client | Marketing and sales |
| Sustainability and EHS | Sustainability page and policy | Management |
The RFI kit to have ready before the request arrives
The kit is a folder of approved answers and documents, each with a version, a date and an owner. With it, answering an RFI means picking and adapting answers you already have. Without it, someone spends a week chasing engineering and quality.
If you sell single-use products, look at the Rx-360 Supplier Assessment Questionnaire. It has six modules, from company and site information to a pre-audit questionnaire and a module for single-use bioprocessing products such as bags, tubing, filters and connectors. Rx-360 says suppliers can complete their response proactively and keep it current, and the tool returns a PDF and a JSON file to share with each customer.
- A company fact sheet in English, with legal name, sites, ownership, headcount and industries served.
- Current certificates as dated PDFs, and a short summary of the quality system.
- A standard answer on GMP status that says exactly what applies to you and what applies to the customer.
- Datasheets, specifications and materials of construction for each product line.
- Signed regulatory statements you are asked for often, kept in one place.
- Your change notification policy and a quality agreement template you can accept.
- Two or three anonymised cases already approved by the clients.
- A library of past answers, sorted by block, with the date each one was approved.

Can we send our ISO 9001 certificate instead of filling in the questionnaire?
Sometimes. In the example table of the APIC guide, an ISO 9001 certificate is preferred, case by case, for medium and low criticality, while the questionnaire is expected for high and medium criticality and decided case by case for low. The buyer decides based on risk, so send the certificate and answer the questionnaire if they ask for it.
Want us to map your last pharma questionnaire against this table? Leave your details and we will tell you which blocks lack a document.
Map my questionnaireHow to show references when everything is under NDA
References are the block suppliers find hardest, because most pharma projects sit under confidentiality agreements. The answer is to prepare them before you need them, not to leave the field empty or to name a client without permission.
An anonymised case with the type of client, the process, the scale, the problem and an outcome the client has approved answers most of what a reference question is after. If a client agrees to take a call, note it in the kit and ask again each time, since people and policies change.
Be precise about anything the buyer can check. The APIC guide notes that regulatory track record can be verified, for example through warning letters. A modest, exact answer earns more trust than a broad claim that quality then has to take apart.
Should we fill in the Rx-360 SAQ before anyone asks?
It helps if you sell single-use components or materials to pharma. Rx-360 says suppliers can complete the questionnaire proactively and keep it current, and the result is a PDF and a JSON file you share with each customer. It does not replace a buyer's own form, but much of the content can be reused.
How long the answers should be and who signs them off
Short answers with a document reference work best. Answer the question asked in two to four sentences, point to the attached document and section, and write not applicable with a one-line reason when a question does not fit your product. Do not paste brochure copy into a quality questionnaire.
Quality signs anything regulatory, sales owns prices and terms, and marketing edits the whole package so it reads in one voice and matches the website. That split matters because the answers can end up in front of an inspector. Point 3.4 of Annex 11 says quality system and audit information about suppliers of computerised systems should be available to inspectors on request.
Keep commercial and quality documents apart as well. The FDA guidance on quality agreements in contract manufacturing, from November 2016, recommends keeping them separate from commercial contracts and notes that they may be reviewed during inspections. Product claims belong in the commercial documents, and the quality agreement belongs to quality.
David Monje, founder of crida studio, ran marketing at TECNIC Bioprocess Solutions for three and a half years and acted as the bridge between engineering, product, sales and the distributors. An answer library only works when those teams agree on the same wording, and someone has to own that work, whether in house or a fractional marketing director.
How your website gets you onto the RFI list
You can only answer an RFI that reaches you. Buyers send RfX requests once they have defined their requirements, so the shortlist is built before the first email. Part of it comes from what buyers find on websites and sometimes from AI assistants that buyers ask for a list of suppliers.
Publish the non-confidential part of your kit. A quality page with dated certificates, a clear statement of what you make and where, a supply chain summary and the line “SAQ response available on request” all answer questions a buyer would otherwise send in writing. They also give AI answers about bioprocess suppliers plain facts to cite.
Keep the website and the kit saying the same thing. If the website lists one capacity and the RFI answer another, quality will ask which one is true, and that question costs time you could have spent on the next stage.
What happens after the RFI?
If the package passes the first review, formal qualification starts. Depending on how critical your product is for the buyer, that can mean a full questionnaire, signed statements, an audit and a quality agreement. Point 5.28 of chapter 5 of the EU GMP guidelines asks for quality requirements to be agreed with starting material suppliers and documented in a quality agreement or specification.
What to do tomorrow
Start with the last RFI or questionnaire you answered. It already holds most of the questions your next buyer will ask, and it shows which answers took longest to collect. If you want help putting it in order, it is the kind of work we do in marketing for biotech and bioprocess companies.
- Sort the questions of your last RFI into the blocks of the table above.
- Give each block an owner and a deadline to approve one standard answer.
- Gather certificates, datasheets and statements into one folder with versions and dates.
- Ask two clients for permission to use an anonymised case.
- If you sell single-use products, complete the Rx-360 SAQ modules that apply to you.
- Publish the non-confidential part on a quality page and link it from each product page.